Overlapping Phases
Overlapping phases, also known as concurrent scheduling or phase overlapping, is a schedule compression technique used in project management to reduce the overall project duration by starting the next phase of a project before the completion of the current phase. This approach challenges the traditional sequential flow of project phases, allowing activities that would typically be scheduled in succession to proceed in parallel. By initiating subsequent tasks before predecessors are fully complete, project teams can significantly shorten the project timeline without altering the project scope. This technique is particularly effective in projects where certain downstream activities can begin with partial information or preliminary outputs from upstream tasks. For example, in construction projects, foundation work might commence before the finalization of structural designs, provided there is sufficient preliminary data to proceed safely. Overlapping phases requires careful coordination and a thorough understanding of task dependencies to manage the increased risks associated with incomplete information. The primary advantage of overlapping phases is the potential for significant time savings, which can be crucial when facing tight deadlines or when trying to capitalize on market opportunities. However, this approach introduces additional risks, such as increased likelihood of rework if changes occur in the upstream tasks that affect the downstream activities already in progress. It may also lead to communication challenges among team members and stakeholders due to the accelerated pace and simultaneous activities. Effective implementation of overlapping phases necessitates robust communication channels, proactive risk management, and flexible project controls. Project managers must ensure that all team members are aware of the overlapping schedules and understand the implications of changes in one phase on subsequent phases. Regular updates and constant monitoring are essential to promptly address issues that arise from the concurrent execution of tasks. In conclusion, overlapping phases can be a powerful tool for schedule compression, enabling faster project completion while maintaining scope and resource levels. When applied judiciously, with careful planning and risk mitigation strategies, it allows project teams to meet aggressive timelines and deliver value more quickly.
Overlapping Phases: A Comprehensive Guide for PMI-SP
Understanding Overlapping Phases in Schedule Compression
Overlapping phases, also known as fast tracking, is a crucial schedule compression technique in project management that can significantly impact project timelines and delivery.
Why Overlapping Phases is Important
Overlapping phases is important because it:
• Reduces overall project duration
• Helps meet tight deadlines and market demands
• Enables earlier delivery of project benefits
• Provides flexibility when dealing with schedule constraints
• Can be essential for time-critical projects
What is Overlapping Phases?
Overlapping phases involves starting a subsequent project phase before the preceding phase is complete. Instead of following a strictly sequential approach where one phase must be 100% complete before starting the next, phases are allowed to overlap, creating parallel work streams.
Traditionally represented in a network diagram as finish-to-start relationships, overlapping phases converts these to start-to-start or finish-to-finish relationships with appropriate lag.
How Overlapping Phases Works
The process of implementing overlapping phases typically involves:
1. Identify Dependencies: Analyze which activities must be strictly sequential and which can overlap
2. Determine Overlap Opportunity: Identify how much of the successor activity can start before the predecessor is complete
3. Assess Risks: Evaluate and plan for potential rework and communication challenges
4. Implement Lead Time: Schedule successor activities to start before predecessor activities finish
5. Monitor Carefully: Establish clear communication channels to manage the increased complexity
Example Scenario:
In construction, foundation work might be 80% complete when framing begins, rather than waiting for 100% completion. This overlap saves time in the overall schedule.
Key Considerations When Implementing Overlapping Phases:
• Risk Increase: Greater risk of rework if early phases require changes
• Resource Conflicts: May require additional resources for parallel activities
• Communication Demands: Requires enhanced communication between teams
• Quality Control: Necessitates robust quality checks at phase interfaces
Exam Tips: Answering Questions on Overlapping Phases
1. Identify Key Terminology: Recognize that "fast tracking" and "overlapping phases" refer to the same technique
2. Understand the Trade-offs: Be prepared to analyze scenarios where overlapping creates benefits (time savings) versus drawbacks (increased risk, potential rework)
3. Differentiate from Crashing: Remember that overlapping phases changes logical relationships, while crashing adds resources to shorten durations
4. Know the Prerequisites: Recognize that overlapping requires:
• Activities that can be performed in parallel
• Clear communication channels
• Effective risk management
5. Focus on Dependencies: Questions often test your understanding of how dependency relationships change when fast tracking
6. Calculation Questions: Practice calculating the impact of lead time on overall schedule duration
7. Contextual Application: Be ready to identify situations where overlapping phases is appropriate or inappropriate
Sample Question Types:
• Scenario-based questions asking which schedule compression technique is most appropriate
• Questions about the risks associated with overlapping phases
• Questions requiring you to identify the correct network diagram representation of overlapping activities
• Situations where you need to recommend mitigation strategies for fast tracking risks
By understanding the concept thoroughly and recognizing its applications and limitations, you'll be well-prepared to answer PMI-SP exam questions on overlapping phases effectively.
Go Premium
PMI Scheduling Professional Preparation Package (2025)
- 3429 Superior-grade PMI Scheduling Professional practice questions.
- Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
- Unlock Effortless PMI-SP preparation: 5 full exams.
- 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
- Bonus: If you upgrade now you get upgraded access to all courses
- Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!