Use of Leads and Lags

5 minutes 5 Questions

The use of leads and lags is a schedule compression technique that involves adjusting the timing relationships between tasks in a project schedule to optimize the overall duration. A lead is an acceleration of the successor activity, allowing it to start before its predecessor activity is fully com…

Test mode:
PMI-SP - Use of Leads and Lags Example Questions

Test your knowledge of Use of Leads and Lags

Question 1

In a project schedule, when is it appropriate to use a lead time between activities?

Question 2

When implementing a lead-lag relationship in a project schedule, what is the most accurate way to represent a 5-day lead?

Question 3

How should a project manager handle a Finish-to-Start relationship between two activities when the successor needs to start before the predecessor is fully complete?

More Use of Leads and Lags questions
12 questions (total)