PMI-SP - Schedule Development Tools and Techniques - Critical Chain Project Management (CCPM)
Intermediate
1/53
During activity duration estimation for a major event management project, your team has access to three estimates for each activity: an optimistic estimate of 2 days, a most likely estimate of 4 days, and a pessimistic estimate of 12 days. Which value represents the expected duration using PERT?