PMI-SP - Schedule Development Tools and Techniques - Critical Chain Project Management (CCPM)
Expert
1/5
In Critical Chain Project Management (CCPM), what is the strategic purpose of implementing drum scheduling in production environments?
a.
To ensure all resources are working at maximum capacity throughout the project lifecycle
b.
To create a balanced workflow by adjusting task durations based on resource availability and capacity constraints
c.
To establish a steady rhythm of work across all departments while maintaining optimal resource utilization and minimizing bottlenecks
d.
To synchronize work release with system constraints to maximize throughput
Expert