Critical Chain Method

5 minutes 5 Questions

The Critical Chain Method (CCM) is an advanced project scheduling technique that modifies the project schedule to account for limited resources. Unlike the Critical Path Method, which focuses solely on task sequencing and durations, CCM incorporates resource constraints into the schedule to create …

Test mode:
PMI-SP - Critical Chain Method Example Questions

Test your knowledge of Critical Chain Method

Question 1

In Critical Chain Project Management (CCPM), what is the primary purpose of feeding buffers?

Question 2

When using Critical Chain Method (CCM), what is the recommended buffer size as a percentage of the critical chain duration?

Question 3

In Critical Chain Method (CCM), what happens to the duration estimates of individual activities?

More Critical Chain Method questions
36 questions (total)