Float (Slack) Calculation

5 minutes 5 Questions

Float, also known as slack, is a key concept in schedule network analysis that refers to the amount of time an activity can be delayed without causing a delay to subsequent activities or the overall project completion date. Calculating float is crucial for understanding the flexibility within a pro…

Test mode:
PMI-SP - Float (Slack) Calculation Example Questions

Test your knowledge of Float (Slack) Calculation

Question 1

In a construction project, the project manager wants to calculate the Free Float of Activity G. The data given are: Activity G - ES (Early Start) = 11, EF (Early Finish) = 19; Activity H - ES (Early Start) = 22. What is the Free Float of Activity G?

Question 2

A project manager is reviewing the critical path of a project. They discovered that the project is running late and need to determine the Total Float of Activity E to identify the impact. What is the Total Float of Activity E considering the following data? Activity E: ES (Early Start) = 4, EF (Early Finish) = 10, LS (Late Start) = 9, LF (Late Finish) = 15.

Question 3

In calculating float values, what statement best describes Total Float in relation to Free Float?

More Float (Slack) Calculation questions
50 questions (total)