Critical Path Method (CPM)

5 minutes 5 Questions

The Critical Path Method (CPM) is a fundamental scheduling technique used to determine the sequence of activities that directly impact the project completion date. It involves mapping out all essential tasks, estimating their durations, and identifying dependencies between them. The critical path is the longest stretch of dependent activities with zero float, meaning any delay in these tasks will directly cause a delay in the project's finish date. Understanding the critical path enables project managers to prioritize resources and focus attention on tasks that are crucial for timely project delivery. In schedule performance analysis, CPM is invaluable for monitoring progress and assessing the impact of deviations from the plan. By regularly updating the project schedule with actual progress data, project managers can identify changes to the critical path and emerging critical activities. This dynamic analysis helps in recognizing potential bottlenecks and delays early, allowing for proactive decision-making. For instance, if a task on the critical path is lagging, managers can allocate additional resources or adjust schedules to mitigate the impact. CPM also facilitates the performance of "what-if" scenarios, assisting in evaluating the effects of proposed changes or unexpected events on the project timeline. This analytical capability supports risk management by highlighting areas where schedule risks are most significant. For a PMI Scheduling Professional, expertise in CPM is essential for effective schedule development, performance analysis, and ensuring that project objectives are met within the allocated timeframes. In essence, the Critical Path Method is a critical tool for project time management. It enhances the ability to control project schedules, optimize resource allocation, and deliver projects successfully by focusing on the most time-sensitive activities.

Critical Path Method (CPM): A Complete Guide

Why Critical Path Method is Important

The Critical Path Method (CPM) stands as a cornerstone technique in project management, particularly for schedule performance analysis in PMI-SP certification. It's important because:

• It identifies the sequence of activities that determine the project's minimum duration
• It highlights which tasks have zero float (slack time)
• It enables project managers to prioritize resources effectively
• It helps in making informed decisions when schedule compression is needed
• It's essential for tracking schedule performance and forecasting completion dates

What is the Critical Path Method?

The Critical Path Method is a mathematical algorithm used to schedule project activities. Developed in the late 1950s, CPM creates a model of the project that includes:

• All activities required to complete the project
• Dependencies between activities (finish-to-start, start-to-start, etc.)
• Duration estimates for each activity
• The longest path through the network diagram, which defines the shortest possible project duration

The critical path consists of activities with zero float, meaning any delay in these activities will delay the entire project.

How Critical Path Method Works

Step 1: Break down the project into activities
List all tasks required to complete the project.

Step 2: Establish dependencies
Determine which activities must precede others.

Step 3: Create a network diagram
Draw a diagram showing the sequence of activities and their relationships.

Step 4: Estimate durations
Assign realistic time estimates to each activity.

Step 5: Calculate Early Start (ES) and Early Finish (EF)
Starting from the project beginning, work forward through the network:
• ES = Latest ES of all predecessor activities
• EF = ES + Duration

Step 6: Calculate Late Start (LS) and Late Finish (LF)
Working backward from the project end:
• LF = Earliest LF of all successor activities
• LS = LF - Duration

Step 7: Calculate float (slack time)
Float = LS - ES (or LF - EF)

Step 8: Identify the critical path
Activities with zero float form the critical path.

Exam Tips: Answering Questions on Critical Path Method (CPM)

1. Calculate forward and backward pass carefully
Most calculation errors happen during these steps. Double-check your math.

2. Remember that the critical path:
• Has the longest duration
• Has zero float
• Determines project completion date
• May change during project execution

3. Multiple critical paths can exist
If two paths have the same duration and zero float, both are critical.

4. Focus on these common question types:
• Identifying the critical path in a network diagram
• Calculating project duration
• Determining impact of delays
• Computing float for specific activities
• Applying schedule compression techniques (crashing/fast tracking)

5. Know the difference between free float and total float
Total float affects the project end date, while free float affects only successor activities.

6. Practice PDM and ADM diagrams
Exams may use either Precedence Diagramming Method or Arrow Diagramming Method.

7. For schedule compression questions:
• Crashing adds resources to reduce duration (increases cost)
• Fast tracking performs activities in parallel (increases risk)
• Always crash critical activities with the lowest crash cost per time unit first

8. Consider resource constraints
The critical path may change when resource limitations are considered (Resource Critical Path).

9. Watch for trick questions
Some questions may provide excessive information or ask about near-critical paths.

10. Draw the network diagram
Even if the question doesn't require it, drawing the network helps visualize the solution.

Test mode:
PMI-SP - Schedule Performance Analysis Example Questions

Test your knowledge of Amazon Simple Storage Service (S3)

Question 1

In a Critical Path Method (CPM) network, what factor determines whether an activity's float can contribute to project acceleration?

Question 2

In Critical Path Method (CPM), what represents the optimal float value when evaluating overlapping finish-to-start relationships between parallel activities?

Question 3

In a project, Activities L (2 days), M (5 days) and N (4 days) must be performed in sequence. Activity O (6 days) can only start after activities L and M are complete. If Activity L is extended by 3 days, how will the critical path be affected?

Go Premium

PMI Scheduling Professional Preparation Package (2025)

  • 3429 Superior-grade PMI Scheduling Professional practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless PMI-SP preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Critical Path Method (CPM) questions
114 questions (total)