Earned Value Management (EVM)

5 minutes 5 Questions

Earned Value Management (EVM) is a project management technique that integrates scope, schedule, and cost parameters to assess project performance and progress objectively. It provides a set of metrics that enable project managers to quantify the value of work completed up to a specific point in ti…

Test mode:
PMI-SP - Earned Value Management (EVM) Example Questions

Test your knowledge of Earned Value Management (EVM)

Question 1

In an EVM analysis, if the project's Schedule Variance (SV) is -$25,000 and the Planned Value (PV) is $100,000, what would be the Schedule Performance Index (SPI) value?

Question 2

In Earned Value Management (EVM), what is the most accurate way to calculate cost variance at completion (VAC)?

Question 3

In a project using Earned Value Management (EVM), which formula provides the most reliable indication of the project's completion efficiency?

More Earned Value Management (EVM) questions
24 questions (total)