PMI-SP - Schedule Performance Analysis - Schedule Baseline and Variance Analysis
Expert
1/12
During schedule variance analysis, what percentage threshold of cumulative float consumption typically triggers a detailed baseline review?
a.
When cumulative float consumption exceeds 75% of the original float
b.
When cumulative float consumption reaches 90% on any parallel path activities in the schedule
c.
When negative float reaches 50% of the total project duration across all critical path activities
d.
When total float consumption surpasses 85% of the baseline buffer allocation for secondary paths