Schedule Variance (SV)

5 minutes 5 Questions

Schedule Variance (SV) is a fundamental metric in project management used to measure the schedule performance of a project. It represents the difference between the value of the work actually completed (Earned Value or EV) and the value of the work that was planned to be completed at a given point in time (Planned Value or PV). The formula for calculating SV is SV = EV - PV. A positive SV indicates that a project is ahead of schedule, while a negative SV signifies that it is behind schedule. SV is essential for tracking the progress of a project because it provides quantifiable data that reflects how well the project is adhering to its planned schedule. Understanding SV allows project managers to identify schedule variances early and take corrective actions promptly. For example, if a project is consistently showing a negative SV, the project manager might need to reallocate resources, adjust timelines, or alter project scope to get back on track. Conversely, a positive SV could allow the team to take on additional work or allocate resources to other areas needing attention. SV is also valuable for communicating project status to stakeholders. By providing concrete numbers, it helps in objectively assessing the project's health and making data-driven decisions. Additionally, analyzing trends in SV over time can reveal systemic issues affecting the schedule performance, such as inefficient processes or resource bottlenecks. It is important to note that SV should be used in conjunction with other performance metrics, like Cost Variance (CV) and the Schedule Performance Index (SPI), to get a comprehensive view of the project's performance. SV alone might not provide the complete picture, especially in projects where costs and schedules are tightly interlinked. In summary, Schedule Variance is a critical concept in schedule performance analysis, enabling effective monitoring and control of the project schedule, facilitating early detection of schedule issues, and supporting informed decision-making to achieve project objectives on time.

Schedule Variance (SV): Understanding, Importance, and Exam Preparation

What is Schedule Variance (SV)?

Schedule Variance (SV) is a critical project management metric that measures the difference between the work completed (Earned Value or EV) and the work scheduled to be completed (Planned Value or PV) at a specific point in time.

Mathematically expressed as: SV = EV - PV

Schedule Variance indicates whether a project is ahead of schedule (positive value) or behind schedule (negative value).

Why is Schedule Variance Important?

1. Performance Measurement: SV provides quantitative data about schedule performance, converting time-based concepts into monetary values for easier comparison.

2. Early Warning System: It serves as an early indicator of schedule problems, allowing project managers to implement corrective actions before minor delays become major issues.

3. Decision Support: SV helps in making informed decisions about resource allocation, timeline adjustments, and scope modifications.

4. Stakeholder Communication: It offers a standardized way to communicate schedule status to stakeholders and sponsors.

5. Trend Analysis: Tracking SV over time reveals performance trends and the effectiveness of corrective actions.

How Schedule Variance Works in Practice

Consider a project with these values at a particular reporting date:
- Planned Value (PV): $50,000
- Earned Value (EV): $45,000

Schedule Variance (SV) = $45,000 - $50,000 = -$5,000

The negative SV (-$5,000) indicates the project is behind schedule. The team has completed $5,000 less work than planned at this point.

Schedule Variance vs. Schedule Performance Index (SPI)

While SV provides an absolute value of schedule deviation, SPI (calculated as EV/PV) gives a ratio that indicates schedule efficiency. Both metrics complement each other in schedule performance analysis.

Limitations of Schedule Variance

1. SV is expressed in monetary terms, not time units, which can sometimes be counterintuitive.

2. SV may not accurately reflect the impact on project completion date, especially for activities not on the critical path.

3. Toward project completion, SV tends to converge to zero even if the project finishes late.

Interpreting Schedule Variance

- SV > 0: Project is ahead of schedule
- SV = 0: Project is on schedule
- SV < 0: Project is behind schedule

Exam Tips: Answering Questions on Schedule Variance (SV)

1. Memorize the Formula: Always remember SV = EV - PV. This is fundamental.

2. Practice Calculations: Be prepared to calculate SV given EV and PV values in various scenarios.

3. Understand Interpretation: Know how to correctly interpret positive, negative, and zero SV values.

4. Connect with Other Metrics: Understand the relationship between SV and other EVM metrics like SPI, CV, and CPI.

5. Look for Trend Questions: Exams often ask about what a series of SV values over time indicates about project performance.

6. Consider Corrective Actions: Be ready to identify appropriate corrective actions based on SV results.

7. Watch for Units: Remember that SV is expressed in currency units, not time units.

8. Common Trap Questions: Be careful with questions that mix up SV with CV (Cost Variance) or confuse the interpretation of positive/negative values.

9. Practice with Charts: Many exam questions present SV data in graphical format, so practice interpreting EVM charts.

10. Time-Phased Analysis: Understand how to analyze SV across different reporting periods to identify trends.

By mastering Schedule Variance concepts and practicing these exam strategies, you'll be well-prepared to handle SV questions in your PMI-SP or other project management exams.

Test mode:
PMI-SP - Schedule Performance Analysis Example Questions

Test your knowledge of Amazon Simple Storage Service (S3)

Question 1

When analyzing Schedule Variance (SV) alongside Cost Variance (CV) in a project, what does SV = +$15,000 and CV = -$10,000 signify?

Question 2

In a project's earned value analysis, if the Schedule Variance (SV) shows -$20,000 in January, -$15,000 in February, and -$5,000 in March, what timing pattern does this suggest for corrective actions?

Question 3

When analyzing Schedule Variance (SV) in a project where tasks have multiple dependencies, how does a +$30,000 value relate to the critical path?

Go Premium

PMI Scheduling Professional Preparation Package (2025)

  • 3429 Superior-grade PMI Scheduling Professional practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless PMI-SP preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Schedule Variance (SV) questions
33 questions (total)