Schedule Variance (SV)

5 minutes 5 Questions

Schedule Variance (SV) is a fundamental metric in project management used to measure the schedule performance of a project. It represents the difference between the value of the work actually completed (Earned Value or EV) and the value of the work that was planned to be completed at a given point …

Test mode:
PMI-SP - Schedule Variance (SV) Example Questions

Test your knowledge of Schedule Variance (SV)

Question 1

When analyzing Schedule Variance (SV) alongside Cost Variance (CV) in a project, what does SV = +$15,000 and CV = -$10,000 signify?

Question 2

In a project's earned value analysis, if the Schedule Variance (SV) shows -$20,000 in January, -$15,000 in February, and -$5,000 in March, what timing pattern does this suggest for corrective actions?

Question 3

When analyzing Schedule Variance (SV) in a project where tasks have multiple dependencies, how does a +$30,000 value relate to the critical path?

More Schedule Variance (SV) questions
33 questions (total)