Schedule Performance Index (SPI) and Schedule Variance (SV)

5 minutes 5 Questions

Schedule Performance Index (SPI) and Schedule Variance (SV) are key metrics derived from Earned Value Management (EVM) that quantitatively measure schedule performance and efficiency. They are instrumental in analyzing how well a project is adhering to its planned schedule. Schedule Variance (SV) …

Test mode:
PMI-SP - Schedule Performance Index (SPI) and Schedule Variance (SV) Example Questions

Test your knowledge of Schedule Performance Index (SPI) and Schedule Variance (SV)

Question 1

A project manager notices that their project has an SPI of 0.92 and the SV is -$15,000 at the current measurement date. What essential action should they take to address this situation?

Question 2

A project reports an SPI of 1.05 in January, 1.15 in February, and 1.25 in March. What does this trend suggest about the project's schedule execution?

Question 3

In a detailed schedule analysis, a project shows SPI = 0.95 and SV = -$10,000. Three months later, SPI = 0.75 and SV = -$45,000. What does this pattern most likely reveal?

More Schedule Performance Index (SPI) and Schedule Variance (SV) questions
12 questions (total)