Schedule Performance Index (SPI) and Schedule Variance (SV) Guide
Introduction to SPI and SV
Schedule Performance Index (SPI) and Schedule Variance (SV) are critical metrics in project management that help project managers assess whether a project is ahead of or behind schedule. These metrics are essential components of Earned Value Management (EVM), a technique used to measure project performance and progress in an objective manner.
Why SPI and SV Are Important
Understanding SPI and SV is crucial because:
• They provide early warning signals of schedule problems
• They allow for objective measurement of schedule performance
• They help quantify the magnitude of schedule deviations
• They support data-driven decision making for corrective actions
• They enable standardized reporting to stakeholders
• They are recognized as best practices in the PMBOK Guide
What Are SPI and SV?
Schedule Variance (SV) is the difference between the work completed (Earned Value or EV) and the work scheduled to be completed (Planned Value or PV) at a given point in time.
SV = EV - PV
• A positive SV indicates the project is ahead of schedule
• A negative SV indicates the project is behind schedule
• SV of zero indicates the project is exactly on schedule
Schedule Performance Index (SPI) is the ratio of work performed to work scheduled.
SPI = EV / PV
• SPI > 1.0: Project is ahead of schedule (favorable)
• SPI < 1.0: Project is behind schedule (unfavorable)
• SPI = 1.0: Project is exactly on schedule
How SPI and SV Work in Practice
To calculate SPI and SV, you need three key data points:
1. Planned Value (PV): The authorized budget assigned to scheduled work
2. Earned Value (EV): The value of work actually completed, expressed in terms of the authorized budget
3. Actual Cost (AC): The actual cost incurred for the work completed
Example Calculation:
If a task was planned to be 50% complete (PV = $5,000) but is actually 40% complete (EV = $4,000):
SV = $4,000 - $5,000 = -$1,000 (behind schedule by $1,000)
SPI = $4,000 / $5,000 = 0.8 (performing at 80% of the planned schedule efficiency)
Interpreting SPI Values:
• SPI of 0.8: The project is progressing at 80% of the planned rate
• SPI of 1.2: The project is progressing 20% faster than planned
Limitations of SPI and SV:
• They can converge to 1.0 and 0 respectively at project completion, even if the project finished late
• They don't account for critical path activities versus non-critical activities
• They're based on budget values, not actual timeline impacts
Exam Tips: Answering Questions on SPI and SV
1. Know the formulas cold: Memorize SV = EV - PV and SPI = EV / PV
2. Remember the interpretations:
• For SV: Positive is good (ahead), negative is bad (behind)
• For SPI: Greater than 1.0 is good, less than 1.0 is bad
3. Practice calculations: Be comfortable making quick calculations with different values
4. Understand the relationships: Know how SPI and SV relate to each other and to other EVM metrics
5. Watch for trick questions: Exam questions might mix up terms or test your understanding of special cases
6. Focus on interpretation: Questions often ask what a specific SPI or SV value indicates about project status
7. Connect to actions: Be prepared to identify appropriate management responses to different SPI/SV values
8. Units matter: SV is expressed in currency units (dollars, euros, etc.), while SPI is a ratio (unitless)
9. Consider trends: Some questions may ask about improving or deteriorating performance based on changing SPI/SV values
10. Related metrics: Understand how SPI and SV relate to CPI (Cost Performance Index) and CV (Cost Variance)
Sample Exam Questions:
1. If EV is $150,000 and PV is $200,000, what is the SPI and what does it indicate?
Answer: SPI = 150,000/200,000 = 0.75, indicating the project is behind schedule, completing only 75% of the work planned.
2. A project has an SV of +$25,000. What does this mean?
Answer: The project is ahead of schedule by $25,000 worth of work.
3. If a project's SPI has gone from 0.85 to 0.75 over the past month, what can you conclude?
Answer: The schedule performance is deteriorating; the project is falling further behind schedule.
Common Mistakes to Avoid:
• Confusing SV with CV (Cost Variance) and SPI with CPI (Cost Performance Index)
• Misinterpreting negative SV or SPI less than 1.0 as positive indicators
• Forgetting that SPI is a ratio while SV is an absolute value
• Assuming that improving SPI/SV automatically means the project will finish on time
By mastering SPI and SV concepts, calculations, and interpretations, you'll be well-prepared to answer related questions on the PMI-SP exam and apply these techniques in real-world project management scenarios.