PMI-SP - Schedule Risk Analysis and Mitigation - Monte Carlo Simulation in Schedule Risk Analysis
Expert
1/12
In a Monte Carlo schedule simulation, what is the most effective way to handle branching decision points in the project network?
a.
Simulate all possible branches simultaneously and aggregate the results based on project milestones
b.
Apply the longest path duration for each branch and add contingency buffers to the final schedule
c.
Apply probability weights to each decision branch and simulate path selection
d.
Calculate the mean duration of all possible branches and use it as a single path in the simulation
Expert