PMI-SP - Schedule Risk Analysis and Mitigation - Sensitivity Analysis in Project Schedules
Expert
1/5
What is the most effective method for validating the quality of scheduling data before including it in a lessons learned repository?
a.
Cross-referencing schedule performance metrics with project outcomes
b.
Requiring senior management approval for all schedule-related lessons before repository inclusion
c.
Implementing automated data validation tools to check for scheduling pattern consistency
d.
Conducting extensive peer reviews of all submitted scheduling documentation and performance data
Expert