Three-Point Estimating and PERT Analysis in Schedule Risk

5 minutes 5 Questions

Three-Point Estimating and Program Evaluation and Review Technique (PERT) Analysis are critical tools in Schedule Risk Analysis, providing a more realistic estimation by considering uncertainty and variability in activity durations. Traditional single-point estimates often fail to account for the i…

Test mode:
PMI-SP - Three-Point Estimating and PERT Analysis in Schedule Risk Example Questions

Test your knowledge of Three-Point Estimating and PERT Analysis in Schedule Risk

Question 1

When analyzing schedule risk using PERT, which formula correctly represents the standard deviation of an activity duration?

Question 2

In PERT analysis, how is the weighted average duration calculated when the most likely estimate appears to be closer to the pessimistic estimate?

Question 3

In a Three-Point PERT estimation scenario, what effect would decreasing the pessimistic estimate while keeping optimistic and most likely estimates constant have on the overall risk assessment?

More Three-Point Estimating and PERT Analysis in Schedule Risk questions
12 questions (total)