Schedule Compression Techniques

5 minutes 5 Questions

Schedule Compression Techniques are methodologies used to shorten the project schedule duration without changing the project scope, in order to meet tight deadlines, recover from delays, or address schedule constraints imposed by stakeholders. The primary techniques include Crashing and Fast Tracking, both of which aim to reduce the overall project timeline while balancing cost and risk considerations. Crashing involves adding additional resources to critical path activities to accelerate their completion. This could mean increasing the workforce, working overtime, or expediting the delivery of materials. While crashing can effectively reduce activity durations, it typically results in increased project costs due to the additional resources required. It is crucial to conduct a cost-benefit analysis to ensure that the costs of crashing do not outweigh the benefits of an earlier project completion. Fast Tracking entails rearranging the project schedule by performing activities in parallel that were originally planned to be sequential. For example, initiating the construction phase before the finalization of all design details. Fast Tracking can significantly shorten the schedule but introduces additional risks and the potential for rework due to overlapping tasks. Communication and coordination become more complex, and any issues in earlier activities can have a cascading effect on subsequent tasks. Both techniques require careful consideration and analysis. Project managers must evaluate the critical path, assess the impact on resources, costs, and risks, and obtain stakeholder approval before implementing schedule compression. Effectively applying these techniques can help meet project deadlines and improve stakeholder satisfaction, but they should be used judiciously to avoid compromising project quality and increasing risks beyond acceptable levels.

Test mode:
PMI-SP - Scheduling Principles and Concepts Example Questions

Test your knowledge of Amazon Simple Storage Service (S3)

Question 1

During schedule compression analysis, a project manager needs to reduce the project duration while minimizing additional costs. Which technique should be implemented first?

Question 2

A project manager needs to identify the best schedule compression technique for specific activities on the critical path. Which factor is most important to consider when choosing between crashing and fast tracking?

Question 3

In a project where multiple schedule compression methods have been applied, what is the most reliable indicator that the optimal compression point has been reached?

Go Premium

PMI Scheduling Professional Preparation Package (2024)

  • 3429 Superior-grade PMI Scheduling Professional practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless PMI-SP preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Schedule Compression Techniques questions
33 questions (total)