Cost Variance Percentage (CV%)

5 minutes 5 Questions

Cost Variance Percentage (CV%) is a key performance indicator in project management that measures the cost efficiency of a project by expressing the Cost Variance (CV) as a percentage of the Earned Value (EV). While Cost Variance provides the absolute difference between the earned value of work per…

Test mode:
PMI-SP - Cost Variance Percentage (CV%) Example Questions

Test your knowledge of Cost Variance Percentage (CV%)

Question 1

If a project activity has a CV% of +25% and a CPI of 1.25, which statement accurately reflects the project's cost performance?

Question 2

Cost Variance Percentage (CV%) is at -15% for a project activity. What does this indicate about the project's cost performance?

Question 3

A project manager is analyzing two critical path activities. Activity A has a CV% of -8% while Activity B has a CV% of -12%. What is the most accurate interpretation of these values?