A project's TCPI calculations show high variability in ranges between 0.8 to 1.4 when analyzed at different work package levels. Which approach would yield the most reliable TCPI assessment?
a.
Sum all individual work package TCPI values and divide by the total number of work packages for overall performance
b.
Calculate TCPI at control account level and analyze patterns across multiple reporting cycles
c.
Focus analysis on work packages with the highest dollar value to determine the overall project TCPI trend
d.
Apply weighted averages to all work package TCPI values and establish a composite baseline for future tracking