Three-Point Estimating

5 minutes 5 Questions

Three-point estimating is a cost estimation technique that acknowledges uncertainties in cost estimates by considering three outcome possibilities for each project component: the most likely (M), the optimistic (O), and the pessimistic (P) estimate. These three points can be derived from historical…

Test mode:
PMP - Three-Point Estimating Example Questions

Test your knowledge of Three-Point Estimating

Question 1

Your project includes a task with an optimistic estimate of 20 days, a most likely estimate of 30 days, and a pessimistic estimate of 50 days. What would be the expected time using Three-Point Estimating?

Question 2

You are observing a construction project where the most probable time to finish a task is 20 days, with optimistic and pessimistic estimates being 15 days and 25 days respectively. Which estimate conveys the median time?

Question 3

In a Three-Point Estimating scenario, you have a task with an optimistic estimate of 5 days, a most likely estimate of 8 days, and a pessimistic estimate of 14 days. The project sponsor wants an estimate that balances risk and optimism. Which formula should you use?

More Three-Point Estimating questions
54 questions (total)