Three-Point Estimating Guide
Three-Point Estimating
What is it: Three-Point Estimating is a tool in Project Management used to estimate the cost or duration of an activity in a project. It leverages three different estimates - the Optimistic (O), the Most Likely (M), and the Pessimistic (P) to arrive at E, the expected estimate. The formula used is E = (O + 4M + P) / 6.
Why it is important: Three-Point Estimating reduces the risk of cost and scheduling overruns by providing a more realistic and reliable estimate. It accounts for uncertainties and risks inherent in project activities.
How it works: By considering different possible scenarios (Optimistic, Most Likely, and Pessimistic), Three-Point Estimating helps in making informed decisions and better planning.
Exam Tips: Answering Questions on Three-Point Estimating
Common questions on Three-Point Estimating often revolve around understanding the concept, the formula, and its application. Here are some tips for answering such questions:
1. Understand the basic concept: Be sure about what Three-Point Estimating entails and its relevance.
2. Know the Formula: The formula - E = (O + 4M + P) / 6 is central. Ensure to commit it to memory and know what each value stands for.
3. Application: Practice questions around applying the formula.
4. Read questions carefully: Understand what the question requires before attempting the answer.
5. Time management: Don't spend excessive time on one question. Be mindful of time.