Cost Variance Analysis

5 minutes 5 Questions

Cost Variance Analysis is a method used by project managers to evaluate the financial performance of a project by comparing its planned costs to its actual costs. This analysis involves calculating cost variances, which represent differences between the budgeted cost (baseline) and actual cost. Cos…

Test mode:
PMP - Cost Variance Analysis Example Questions

Test your knowledge of Cost Variance Analysis

Question 1

A project manager calculates the cost performance index (CPI) to be 1.25, and the schedule performance index (SPI) to be 1.10. What does this indicate?

Question 2

A project manager noticed that the project's cost performance index (CPI) is 0.80, and the actual cost of the project is $150,000. What is the current earned value of the project?

Question 3

A project manager reviewing the cost performance of a project finds the actual cost (AC) to be $160,000, earned value (EV) to be $150,000, and the planned value (PV) at $145,000. Which conclusion can be drawn regarding the cost variance (CV) in this scenario?

More Cost Variance Analysis questions
21 questions (total)