PMP - Cost Management - Project Cost Management Plan
Advanced
1/22
In the Project Cost Management Plan, what is the primary purpose of establishing a cost baseline?
a.
It outlines the procedures for reallocating funds during project execution.
b.
It serves as a reference point for measuring project cost performance.
c.
It ensures all project budgets are distributed proportionally across tasks.
d.
It defines the maximum allowable budget that cannot be exceeded.