Actual Cost

5 minutes 5 Questions

Actual Cost (AC), also known as Actual Cost of Work Performed (ACWP), is the total cost incurred for a specific activity or work done during the project. It includes direct costs such as labor and materials, and indirect costs such as overheads and equipment rental. In EVM, AC is compared with EV a…

Test mode:
PMP - Actual Cost Example Questions

Test your knowledge of Actual Cost

Question 1

Actual cost (AC) is the total cost _______ to complete project work as of a specific date.

Question 2

A company is renovating its office which was initially budgeted to cost $100,000. Halfway through the project, the company has spent $35,000 on materials and $30,000 on labor. What is the Actual Cost?

Question 3

A project manager oversees a software project with a budget of $50,000. The team has spent $25,000 so far, but the project is only 30% complete. What is the Actual Cost?

More Actual Cost questions
21 questions (total)