Budget at Completion

5 minutes 5 Questions

Budget at Completion (BAC) represents the total approved budget for a project, encompassing all authorized work components, including labor, materials, and other associated costs. It is a baseline value used to monitor and control the project's financial performance throughout its life cycle. Compa…

Test mode:
PMP - Budget at Completion Example Questions

Test your knowledge of Budget at Completion

Question 1

You are overseeing a renovation project with an initial budget of $500,000. The project is 40% complete, but spending has already reached $240,000. If the expenditure continues at the same pace, what will the expected budget at completion be?

Question 2

As a project manager, you're overseeing a software development project that was initially budgeted at $500,000. The project is currently 40% complete but the actual cost has already reached $240,000. If the expenditure continues at the same pace, what would be the budget at completion?

Question 3

The project manager of a software development project notices that the expenses reached $50,000 to complete 20% of the project, which originally had a $200,000 budget. What is the estimated budget at completion?

More Budget at Completion questions
31 questions (total)