Control Account

5 minutes 5 Questions

A Control Account (CA) is a management control point in a project where scope, cost, and schedule management converge. It is a consolidated report of multiple subprojects, work packages, and project management processes, helping project managers maintain an organized approach to managing projects. …

Test mode:
PMP - Control Account Example Questions

Test your knowledge of Control Account

Question 1

You're handling a project with a Control Account (CA) of $1,500,000. The project has reached 60% completion, while the Actual Cost (AC) totals to $900,000 and the Earned Value (EV) is $850,000. As the project manager, what would be the optimal next step?

Question 2

A large aerospace project has a control account of $5 million for developing a new satellite component. At the 40% completion mark, the Earned Value (EV) is $1.8 million, while the Actual Cost (AC) has reached $2.2 million. The Schedule Performance Index (SPI) is 0.9, indicating a slight delay. The project team has identified potential design improvements that could enhance the component's performance but would require additional resources. As the project manager, what is the most appropriate course of action?

Question 3

You have a control account budget at completion of $80,000. The project has progressed 30%, and you spent $28,000. How should you proceed?

More Control Account questions
22 questions (total)