Cost Variance
Cost Variance (CV) refers to the difference between the earned value and the actual cost of a project at any given time. It is a crucial EVM tool that depicts whether a project is over or under budget. A positive CV signifies that the project is under budget, while a negative CV points to it being …
PMP - Cost Variance Example Questions
Test your knowledge of Cost Variance
Question 1
In a project, the Earned Value (EV) is $750,000 and the Actual Cost (AC) is $700,000. What does the Cost Variance (CV) indicate about the project's financial performance?
Question 2
As a project manager, the Earned Value (EV) of your project is $16,000, and the Actual Cost (AC) is $12,000. What is the Cost Variance of the project?
Question 3
You are a project manager working on a software development project. The project has an actual cost of $120,000 and earned value of $110,000. The planned value is $100,000. What is the cost variance?