Earned Value

5 minutes 5 Questions

Earned Value (EV) is a comprehensive metric used to measure a project's health, progress, and performance. It is the actual value of work accomplished until the present moment, based on the initial estimated cost for the given scope. It helps in understanding how much value a project has generated compared to the costs that have been incurred. EV is a key component of Earned Value Management (EVM), which is crucial for managing the costs and budgets of complex projects effectively.

Earned Value Management (EVM) Guide from PMBOK 7th Edition

Earned Value Management is a critical concept in the Project Management Professional (PMP) certification exam. EVM helps measure project performance and progress. Following are some key points:

Importance: EVM allows project managers to track the true cost of the project against the plan. It gives an accurate picture of the project's health, alerting managers when costs are not aligning with the work accomplished. This can pinpoint issues early and provide time for corrective action.

Concept: EVM combines schedule performance and cost performance to answer the question, 'What did we get for the money spent?' It results in metrics, namely Schedule Variance, Cost Variance, Schedule Performance Index, and Cost Performance Index, which help in forecasting, variance analysis and control. The three components of EVM are Planned Value (PV), Actual Cost (AC), and Earned Value (EV).

Workings: Calculate EV as the percentage of the total budget assigned to a task multiplied by the percentage of the work completed. The variance analysis then uncovers project performance and the conformance to the initial projections.

Exam Tips: Understand the formulas (like SPI=EV/PV, CPI=EV/AC etc.) and their implications. Do not memorize them, grasp their essence. Be comfortable with using some basic math for computations. Expect scenario-based questions where you need to compute variances or indexes.

Remember: The greater the variance, the greater the risk. Practice a lot of mock test questions based on this concept and learn to apply EVM on a case-to-case basis.

Test mode:
PMP - Earned Value Management Example Questions

Test your knowledge of Amazon Simple Storage Service (S3)

Question 1

You're managing a complex IT infrastructure upgrade project with a Budget at Completion (BAC) of $500,000. After 6 months, the project is 40% complete, with an Earned Value (EV) of $200,000 and Actual Cost (AC) of $250,000. The project sponsor is concerned about the cost overrun and wants to know the projected final cost. You decide to use the Estimate at Completion (EAC) formula that assumes the current Cost Performance Index (CPI) will continue. What is the most accurate EAC for this project?

Question 2

In a project with a Budget at Completion (BAC) of $100,000, the Earned Value (EV) is $40,000 and the Actual Cost (AC) is $50,000. What is the Cost Performance Index (CPI)?

Question 3

A project to develop a new mobile application has a Budget at Completion (BAC) of $500,000. After 6 months, the Earned Value (EV) is $200,000, and the Actual Cost (AC) is $240,000. The project manager needs to forecast the final cost and assess the project's financial health. The sponsor is concerned about potential budget overruns and wants to know if additional funds should be allocated. Using Earned Value Management (EVM) principles, what is the most appropriate action for the project manager to take based on this information?

Go Premium

Project Management Professional Preparation Package (2025)

  • Earn 35 PDUs needed for your PMP certification
  • 9524 Superior-grade Project Management Professional practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless PMP preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Earned Value questions
22 questions (total)