Estimate at Completion

5 minutes 5 Questions

Estimate at Completion (EAC) is a projection of the total cost of a project at its completion, taking into account both the actual costs incurred so far and the remaining cost estimates. EAC can vary based on assumptions, risks, and the project's current performance. Several formulas can be used to…

Test mode:
PMP - Estimate at Completion Example Questions

Test your knowledge of Estimate at Completion

Question 1

You are the project manager for a building project. The BAC is $250,000, the AC stands at $100,000, with an EV of $80,000. What should the EAC be given the current project performance?

Question 2

You are the project manager for a road construction project with a budget at completion (BAC) of $300,000. The project's actual cost (AC) is $90,000, and the earned value (EV) is $75,000. What estimate at completion (EAC) should you anticipate?

Question 3

A project has a BAC of $150,000 and a CPI of 0.89. Should the project continue at its current performance, what would you estimate the EAC to be?

More Estimate at Completion questions
34 questions (total)