Estimate to Complete (ETC) in Earned Value Management
The 'Estimate to Complete' (ETC) is a crucial component in the field of project management. It is significant because it provides an estimation of the funds required to complete the remaining part of the project.
What it is: In the context of earned value management, Estimate to Complete (ETC) is the anticipated cost to complete the remaining work in a project. It is calculated by subtracting the actual cost (AC) till date from the Estimate at Completion (EAC).
How it works: ETC = EAC - AC. Here, the EAC is the total estimated cost of the project at completion, and AC is the actual cost incurred till the current reporting period.
It is a key element in project management that helps in understanding whether the project is on track concerning budget and if there are any potential budget overruns.
Guide to answer Estimate to Complete (ETC) questions:
Understanding the concept thoroughly is crucial in answering ETC related questions. Remember the formula for ETC, practice calculation-based problems, and carefully read the question to interpret what is asked.
Exam Tips:
1. Understand the relationship between ETC, EAC, and AC.
2. Practice problems related to ETC to build familiarity.
3. In the exam, take care to read the question carefully and understand what is asked before answering.
4. Do not confuse ETC with Estimate at Completion or any other similar terms.
5. Always remember, ETC is about future expenditure, not past.