Estimate to Complete
Estimate to Complete (ETC) is a concept used to forecast the cost required to complete the remaining work in a project. It represents an updated estimate of the project budget based on its current performance and any changes in scope or resources. ETC can be calculated by subtracting the Actual Cos…
PMP - Estimate to Complete Example Questions
Test your knowledge of Estimate to Complete
Question 1
During a project, the project manager wants to estimate the total cost required to complete the remaining work. Which of the following techniques should the project manager use for this purpose?
Question 2
In a project where the Estimate at Completion (EAC) is $1,500,000 and the Actual Cost (AC) is $900,000, what is the Estimate to Complete (ETC)?
Question 3
In a construction project, the initial budget was pegged at $3,000,000 across a 12-month period. After 6 months, the project has consumed $1,800,000 and achieved 50% of the project scope. What's your Estimate to Complete (ETC)?