Estimate to Complete

5 minutes 5 Questions

Estimate to Complete (ETC) is a concept used to forecast the cost required to complete the remaining work in a project. It represents an updated estimate of the project budget based on its current performance and any changes in scope or resources. ETC can be calculated by subtracting the Actual Cos…

Test mode:
PMP - Estimate to Complete Example Questions

Test your knowledge of Estimate to Complete

Question 1

During a project, the project manager wants to estimate the total cost required to complete the remaining work. Which of the following techniques should the project manager use for this purpose?

Question 2

In a project where the Estimate at Completion (EAC) is $1,500,000 and the Actual Cost (AC) is $900,000, what is the Estimate to Complete (ETC)?

Question 3

In a construction project, the initial budget was pegged at $3,000,000 across a 12-month period. After 6 months, the project has consumed $1,800,000 and achieved 50% of the project scope. What's your Estimate to Complete (ETC)?

More Estimate to Complete questions
33 questions (total)