Planned Value

5 minutes 5 Questions

Planned Value (PV), also known as Budgeted Cost of Work Scheduled (BCWS), represents the estimated value of the scheduled work at any given point in time during the project. It is used as a performance baseline for determining how well a project is progressing in terms of cost, time, and scope. Com…

Test mode:
PMP - Planned Value Example Questions

Test your knowledge of Planned Value

Question 1

You are managing a project with a budget of $500,000 to be completed in 5 months. You are currently in the first month. What is the Planned Value (PV)?

Question 2

A project with a 12-month schedule has a total budget of $240,000. By the sixth month, you only completed half of the activities with a total cost of $100,000. What is the Planned Value (PV)?

Question 3

A project has a total budget of $500,000 and is scheduled for 12 months. After 6 months, the project manager calculates the Planned Value (PV). What is the PV?

More Planned Value questions
21 questions (total)