Planned Value (PV), also known as Budgeted Cost of Work Scheduled (BCWS), represents the estimated value of the scheduled work at any given point in time during the project. It is used as a performance baseline for determining how well a project is progressing in terms of cost, time, and scope. Com…Planned Value (PV), also known as Budgeted Cost of Work Scheduled (BCWS), represents the estimated value of the scheduled work at any given point in time during the project. It is used as a performance baseline for determining how well a project is progressing in terms of cost, time, and scope. Comparing PV with the actual cost and earned value indicates if the project is on schedule and within the planned budget. PV plays a vital role in EVM, helping project managers track the financial performance and making informed decisions.
PMBOK Guide 7th Edition: Planned Value (PV)
1. Importance: Understanding Planned Value (PV) is vital as it is an essential aspect of project cost management. PV indicates how much of the project's budget should have been spent according to the schedule. It aids in measuring the project's progress from a cost perspective so that managers can make informed decisions. 2. Definition: Planned Value (PV), often referred to as Budgeted Cost of Work Scheduled (BCWS), is the authorized budget assigned to scheduled work to be accomplished for an activity or Work Breakdown Structure (WBS) component. 3. Working: To calculate PV, multiply the planned percentage of completed work by the total project budget. PV works as an indicator to show the value of the work that was supposed to be accomplished according to the project's schedule. 4. Answering exam questions: For the exam, remember the formula PV = (Planned % Complete) x (Total Budget). Questions might present you with the planned percentage of completed work and the total budget and ask you to calculate the PV. 5. Exam Tips: - Always remember the formula and the meaning of each term. - Practice questions on PV to get the concept clear. - Remember the difference between PV, Earned Value (EV), and Actual Cost (AC). - In case of a question presenting a scenario, break it down to compute the PV.
You are managing a project with a budget of $500,000 to be completed in 5 months. You are currently in the first month. What is the Planned Value (PV)?
Question 2
A project has a total budget of $500,000 and is scheduled for 12 months. After 6 months, the project manager calculates the Planned Value (PV). What is the PV?
Question 3
A project with a 12-month schedule has a total budget of $240,000. By the sixth month, you only completed half of the activities with a total cost of $100,000. What is the Planned Value (PV)?
Pass Your PMP Exam on the First Try
13,500+ questions aligned with ECO & PMBOK 7
Earn 35 PDUs: Practice counts toward the 35 contact hours required for your PMP application
All 3 ECO Domains: People (42%), Process (50%), and Business Environment (8%) — weighted like the real exam
180-Question Mock Exams: Full-length simulations matching the real PMP exam format and time pressure
100% Satisfaction Guaranteed: Full refund if unsatisfied
Risk-Free: 7-day free trial with all premium features!