Quantitative Risk Analysis

5 minutes 5 Questions

Quantitative Risk Analysis is a numerical approach to assessing the potential impact of identified risks on project objectives, such as cost, schedule, or performance. This analysis employs statistical, mathematical, or simulation techniques to estimate the probability and consequence of each risk …

Test mode:
PMP - Quantitative Risk Analysis Example Questions

Test your knowledge of Quantitative Risk Analysis

Question 1

In quantitative risk analysis, the technique that uses a model to combine individual risk probabilities and impacts into an overall risk profile for the project is called ___________.

Question 2

A project manager is planning a database migration project. He has determined the mean duration is 20 days with a standard deviation of 5 days. If he wants to estimate the probability that the project will take more than 25 days, what method of quantitative risk analysis should he use?

Question 3

During a construction project, an identified risk is a delay in delivery of critical materials. This risk could potentially delay the project by 10 days with a probability of 0.3. What is the expected time delay due to this risk?

More Quantitative Risk Analysis questions
48 questions (total)