Float Calculation

5 minutes 5 Questions

Float, also known as 'slack,' is a scheduling concept used to determine the flexibility and availability of time for a specific activity or task in a project. Float calculation involves the evaluation of the total amount of time an activity can be delayed without affecting the project's overall com…

Test mode:
PMP - Float Calculation Example Questions

Test your knowledge of Float Calculation

Question 1

A project manager discovered that activity D has a Free Float of 4 days but wanted to verify the calculation. With the given data, determine if the Free Float was correctly calculated: Activity D - Early Start (ES) = 6, Early Finish (EF) = 15; Activity F (successor of Activity D) - Early Start (ES) = 19.

Question 2

In a project, the project manager has provided the new data for Activity Z which shows Early Start (ES) = 12, Early Finish (EF) = 20; Activity Y - Early Start (ES) = 23, and the manager wants to confirm the Free Float of Activity Z. What should be the correct Free Float of the activity?

Question 3

In an engineering project, Activity K has an ES of 15 and an EF of 23, Activity L has an ES of 30 and EF of 40. What is the Total Float of Activity K in this case?

More Float Calculation questions
50 questions (total)