Schedule Network Analysis
Schedule Network Analysis is a technique used to identify the sequence of project activities, estimate their duration, and establish the relationships between them. This process involves building a visual representation called a project network diagram that illustrates the dependencies and intercon…
PMP - Schedule Network Analysis Example Questions
Test your knowledge of Schedule Network Analysis
Question 1
A project manager is overseeing a software development project with several interdependent tasks. During the project, an unexpected regulatory change necessitates adding additional compliance tasks to the schedule. These new tasks are mandatory and must be completed before certain existing tasks can proceed. The project manager needs to update the schedule to accommodate these changes and understand the impact on the project timeline. What should the project manager do?
Question 2
In a manufacturing project, the assembly of parts cannot commence until five days after the materials are delivered due to quality inspections. The project manager wishes to adjust the project schedule to reflect this required delay between material delivery and assembly. Which scheduling adjustment is appropriate in this case?
Question 3
During the execution of a large construction project, the project manager notices that the timelines of several non-critical activities are overlapping, causing potential resource conflicts. To optimize resource allocation without affecting the project completion date, what should the project manager do?