Schedule Variance

5 minutes 5 Questions

Schedule Variance (SV) is a performance metric used to evaluate the difference between the planned and actual project schedule. It is calculated by subtracting the planned value (PV) from the earned value (EV). A positive SV indicates that the project is ahead of schedule, and a negative SV indicat…

Test mode:
PMP - Schedule Variance Example Questions

Test your knowledge of Schedule Variance

Question 1

You are managing a project with a planned value of $30,000 and an earned value of $25,000. If the schedule variance is -$5,000, what can you conclude?

Question 2

Your project has an earned value of $5,000, a planned value of $6,000, and an actual cost of $7,000. What is the schedule variance and the schedule performance index?

Question 3

Schedule Variance (SV) is calculated by subtracting the [BLANK] from the Earned Value (EV).

More Schedule Variance questions
22 questions (total)