Schedule Variance
Schedule Variance (SV) is a performance metric used to evaluate the difference between the planned and actual project schedule. It is calculated by subtracting the planned value (PV) from the earned value (EV). A positive SV indicates that the project is ahead of schedule, and a negative SV indicat…
PMP - Schedule Variance Example Questions
Test your knowledge of Schedule Variance
Question 1
You are managing a project with a planned value of $30,000 and an earned value of $25,000. If the schedule variance is -$5,000, what can you conclude?
Question 2
Your project has an earned value of $5,000, a planned value of $6,000, and an actual cost of $7,000. What is the schedule variance and the schedule performance index?
Question 3
Schedule Variance (SV) is calculated by subtracting the [BLANK] from the Earned Value (EV).