Complete Guide to Rolling Wave Planning for PMP Exam
Importance:
Rolling Wave Planning is a crucial component of the PMBOK Guide Seventh Edition. It's a project management technique used for extended planning horizons. It's advantageous for situations where tasks can’t be defined accurately far in advance due to the fast-changing environment or due to uncertainties.
What it is:
Rolling Wave Planning is a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail, while the work in the future is sketched at a high level. It's a schedule development factor that deals with the planning schedule activities of a project.
How it works:
The details of the work to be performed are planned as the work nears. As more details become available, the work packages for future periods are decomposed into scheduled activities.
Exam Tips:
Understanding the concept: Examiners want to see that you understand the mechanism and the scenario when to use Rolling Wave Planning. Be sure to clarify its use in the context of uncertain or dynamic projects.
Application: Expect to answer questions how Rolling Wave Planning applies, with given scenarios. The key is to identify that work packages for the foreseeable future are detailed, while those for later stages are at a higher level.
Variations: Some questions might come from variations of Rolling Wave Planning, like its use in agile methodologies.