PMP - Scope Baseline - Create WBS Process
Intermediate
1/5
During the Create WBS process, a project manager is determining the appropriate level of detail for decomposing work packages. Which criterion should the project manager use to decide when to stop decomposing?
a.
When work packages are detailed enough to estimate costs and durations accurately.
b.
When tasks are broken down until they can be completed within a few hours.
c.
When each work package aligns with a specific department's responsibilities only.
d.
When work packages reach the smallest possible units, regardless of practicality.
Intermediate