The WBS Dictionary is a comprehensive document that explains and provides additional details for each component within the Work Breakdown Structure. These details may include the work package identifier, any assigned resources, a description of the specific work or deliverable, and any relevant qua…The WBS Dictionary is a comprehensive document that explains and provides additional details for each component within the Work Breakdown Structure. These details may include the work package identifier, any assigned resources, a description of the specific work or deliverable, and any relevant quality, time, and cost estimates. The WBS Dictionary ensures that all project stakeholders have a clear and consistent understanding of the work packages and their requirements. It facilitates communication among project team members, enabling better decision-making, coordination, and control throughout the project lifecycle.
Guide: Understanding and Answering Questions on WBS Dictionary
What is WBS Dictionary: The WBS Dictionary is a crucial component of the project management process as outlined in the PMBOK Guide Seventh Edition. It gives a detailed description of the work to be done for each element in the Work Breakdown Structure (WBS), providing a shared understanding among stakeholders. Why it is important: It is important because it helps clarify the boundaries of each component in the WBS, preventing scope creep and ensuring everyone is on the same page about what work is included (and not included). It provides detailed scope descriptions, deliverables, and thoroughly outlines tasks necessary to achieve project objectives. How it works: Once a WBS is created, each component is further elaborated in the WBS dictionary with detailed component descriptions, work details, who is responsible, resources required, and other relevant information. It serves as a guide throughout the project lifecycle, ensuring all aspects of scope are properly managed. How to answer questions regarding WBS Dictionary in an exam: When asked about the WBS dictionary in exams, highlight its contribution in providing clear, actionable information about each WBS component. Mention how it helps in scope management and preventing scope creep. Use related terminology as used in PMBOK Guide. Exam Tips: Answering Questions on WBS Dictionary: Read the question carefully and understand what is asked. Make sure you understand the role of WBS dictionary in scope management and how it impacts project success. Tip 1: If the question revolves around preventing scope creep or ensuring everybody has the same understanding of work, the answer often involves WBS dictionary. Tip 2: You might be asked to identify what information is included in a WBS dictionary. In such cases, recollect details like resource requirements, responsibility assignments and work descriptions. Tip 3: Questions might focus on how a PM uses the WBS Dictionary - be prepared to discuss how it guides project work and aids in keeping the project on track.
A construction project manager analyzes a WBS Dictionary entry and discovers that it lacks critical cost estimation data. Which action should be taken?
Question 2
Before finalizing the WBS Dictionary for a software development project, the project manager receives a last-minute requirement change. How should this change be incorporated into the WBS Dictionary?
Question 3
A project manager is leading a large-scale event planning project. What steps should be taken when creating the WBS Dictionary?
🎓 Unlock Premium Access
Project Management Professional + ALL Certifications
🎓 Access to ALL Certifications: Study for any certification on our platform with one subscription
Earn 35 PDUs needed for your PMP certification
10338 Superior-grade Project Management Professional practice questions
Unlimited practice tests across all certifications
Detailed explanations for every question
PMP: 5 full exams plus all other certification exams
100% Satisfaction Guaranteed: Full refund if unsatisfied
Risk-Free: 7-day free trial with all premium features!