Variance Analysis

5 minutes 5 Questions

Variance Analysis is a technique used in project management to identify and analyze the differences between planned and actual project performance, particularly concerning the project scope, time and cost. It involves comparing the planned work, costs or schedule against the actual progress, identi…

Test mode:
PMP - Variance Analysis Example Questions

Test your knowledge of Variance Analysis

Question 1

Working on a construction project, the actual cost was found to be $40,000. However, the earned value was quantified at $30,000 and a planned value of $20,000. How would you interpret this?

Question 2

You, as the project manager, are presented with an actual cost of $100,000. The earned value obtained is $200,000 but the planned value states as $300,000. How would you respond based on the variance analysis?

Question 3

In a hardware development project, the earned value is found to be $8,000, and the actual cost is $10,000. However, the planned value was only $7,000. What does this tell about the project's status?

More Variance Analysis questions
57 questions (total)