During the Monitor Stakeholder Engagement process, a project manager discovers that the current engagement strategies are not effectively encouraging participation from several key stakeholders. What is the most appropriate action for the project manager to take?
a.
Escalate the engagement issues to higher management for resolution.
b.
Maintain the existing engagement plan without changes.
c.
Adjust the stakeholder engagement plan to better meet stakeholders' needs.
d.
Revise the stakeholder register to remove disengaged stakeholders.