Change Budget
A Change Budget in PRINCE2 is a financial provision specifically allocated to fund the implementation of requests for change and for resolving issues that might arise during the project. It's essentially a contingency fund designated for managing changes rather than for addressing general cost overruns or risks. The Change Budget is typically established at the beginning of the project and is controlled by the Project Board or the Change Authority if one has been appointed. The existence of a Change Budget acknowledges that change is inevitable in projects and provides a mechanism to handle changes without constantly revisiting the overall project budget. When a request for change is approved, the cost of implementing it can be drawn from this budget rather than requiring new funding approvals or reallocations from other project activities. This approach streamlines the change control process and can speed up decision-making. The size of the Change Budget should be proportional to the project's complexity, duration, and certainty of requirements. Projects with uncertain requirements or operating in rapidly changing environments typically benefit from larger Change Budgets. The management of this budget should be transparent, with clear reporting on its utilization and remaining funds. It's important to note that the Change Budget is different from management reserves or contingency funds, which are typically used for managing risks or unexpected cost variances within the existing scope of the project.
Change Budget in PRINCE2: Navigating Financial Allocation for Changes
Why the Change Budget is Important
The Change Budget is a crucial financial component in PRINCE2 projects as it provides a dedicated financial reserve for funding requests for change (RFCs) during project execution. It acknowledges the reality that most projects will face changes and ensures there's allocated funding to implement approved changes rather than constantly revising the project budget or seeking additional funds.
What is the Change Budget?
The Change Budget is a financial provision specifically set aside to fund the implementation of requests for change (RFCs) that are approved during a project. It's separate from:
- The project budget (which funds the planned work)
- Risk budget (which covers specific identified risks)
- Contingency (which addresses unknown risks)
The Change Budget is formally established during project initiation and is controlled by the Project Board, who determine how much authority they delegate to the Project Manager for approving change costs.
How the Change Budget Works
1. During project initiation, the Project Board allocates a specific amount of funds as the Change Budget
2. When a Request for Change is submitted, its financial impact is assessed
3. If the change is approved, the cost is funded from the Change Budget
4. The Project Manager can approve changes up to a certain financial threshold (set by the Project Board)
5. Changes exceeding this threshold require Project Board approval
6. The Executive remains responsible for ensuring the project remains viable as changes are approved
7. Changes are formally logged in the Configuration Management system and impact assessments are done before approval
8. The Change Budget should be monitored and reported on as part of regular progress reports
Key Principles for the Change Budget
- It's controlled by the Change Authority (often the Project Board)
- It should be proportionate to the expected level of change in the project
- It helps maintain project viability by providing a controlled approach to funding changes
- It supports the PRINCE2 principle of "Manage by Exception" by setting clear financial tolerances
Exam Tips: Answering Questions on Change Budget
1. Differentiate between budgets: Be clear about the distinction between change budget, risk budget, and the main project budget. They serve different purposes.
2. Remember the control framework: Questions may test your understanding of who controls the Change Budget (Project Board) and who can approve changes at different financial levels.
3. Link to other themes: The Change Budget connects to the Change theme, Progress theme (for reporting), and Plans theme (for adjusting plans). Exam questions often test these interdependencies.
4. Focus on project viability: Remember that the Executive must ensure the project remains viable with each change - this is a frequent exam topic.
5. Understand delegation: Know that the Project Board can delegate change approval authority to the Project Manager up to set limits, or to a Change Authority.
6. Recognize timing: The Change Budget is established during project initiation and documented in the Project Initiation Documentation (PID).
7. Connect to configuration management: All changes must be properly recorded in the configuration management system - this relationship may be tested.
When answering multiple-choice questions, look for answers that emphasize controlled management of changes, proper authorization procedures, and maintenance of business justification.
Go Premium
PRINCE2 Foundation Preparation Package (2025)
- 1825 Superior-grade PRINCE2 Foundation practice questions.
- Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
- Unlock Effortless PRINCE2 Foundation preparation: 5 full exams.
- 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
- Bonus: If you upgrade now you get upgraded access to all courses
- Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!