If a project has a commercial relationship between the customer and supplier organizations, what is the recommended approach for the Project Board composition?
a.
Each organization should have its own Project Board member(s)
b.
One organization must appoint all Project Board members while the other provides only advisory support
c.
The Executive role should be shared between both organizations with equal authority
d.
The Project Board should be expanded to include legal representatives from both parties