In which document is the Continued Business Justification primarily maintained and updated throughout the project?
a.
The Business Case document, which is updated at each stage boundary.
b.
The Project Brief, which establishes the initial project concept and approach.
c.
The Project Initiation Documentation excluding the Business Case sections.
d.
The Daily Log, where all informal issues, requirements and decisions are recorded.