What should a Team Manager do if they identify that a product cannot be delivered according to the agreed specification in the Work Package during the Managing Product Delivery process?
a.
Continue development and document the deviations in the End Stage Report for later review
b.
Update the Team Plan with extended timelines and proceed with development until completion
c.
Raise an issue to the Project Manager and propose corrective actions
d.
Modify the quality criteria in the Product Description to match what can realistically be delivered