PRINCE2 Practitioner - Applying PRINCE2 Processes - Closing a Project
Intermediate
1/5
According to PRINCE2, what is the key consideration when determining whether to escalate a change for Project Board approval?
a.
Whether the change requires formal documentation in the Issue Register and Configuration Item Records
b.
Whether the change would result in a fundamental modification to the project approach defined in the Project Initiation Documentation
c.
Whether the change has been requested by the Senior User representing business interests
d.
Whether the change exceeds the tolerances delegated to the Change Authority