When should the Project Board escalate matters to Corporate or Programme Management according to PRINCE2?
a.
When all project deliverables have been approved and the project is ready for closure
b.
When the project exceeds or is forecast to exceed the tolerances set by Corporate or Programme Management
c.
When the project team requests additional resources to complete their assigned work packages
d.
When any deviation from the project plan occurs, regardless of tolerance levels