According to PRINCE2, which information should be included in a Checkpoint Report during the Managing Product Delivery process?
a.
The complete risk profile assessment for the current stage and its relation to corporate risk tolerance
b.
A detailed description of all quality management activities applied to each product
c.
Progress against the Work Package activities and products
d.
The business case justification for all products in development