PRINCE2 Practitioner - Applying PRINCE2 Processes - Starting up a Project
Intermediate
1/5
In PRINCE2, what is the recommended approach for estimating activities in a project plan?
a.
Use expert judgment as the sole method of estimation to expedite the planning process
b.
Use comparative estimating based on similar previous projects
c.
Apply parametric estimating only when the Project Manager specifies it is necessary
d.
Always apply bottom-up estimating for all activities regardless of project size