PRINCE2 Practitioner - PRINCE2 Principles in Context - Learn from Experience
Intermediate
1/45
According to PRINCE2, which of the following BEST describes the relationship between the Project Manager and the Executive in terms of project decisions?
a.
The Project Manager consults with the Executive on all operational decisions before implementing any project activity
b.
The Executive delegates all decision-making authority to the Project Manager and only receives status reports at stage boundaries
c.
The Project Manager manages day-to-day decisions while the Executive makes decisions on key issues that exceed tolerances
d.
The Project Manager and Executive jointly approve all decisions through a formal consensus-building process