PRINCE2 Practitioner - PRINCE2 Principles in Context - Manage by Exception
Beginner
1/5
In a PRINCE2 project, if an exception occurs, what type of plan does the Project Manager need to prepare for Project Board approval?
a.
Contingency Plan showing all alternative paths forward
b.
Exception Plan
c.
Recovery Plan with revised tolerances and targets
d.
Stage Plan with extended tolerances