Release Planning

5 minutes 5 Questions

Release Planning involves deciding on a commitment point at which a version of the product is to be released and involves predicting or forecasting the functionality that will be available at the end of the release. Though Scrum does not formally have a 'Release Planning' event, it is a real-world …

Test mode:
PSM I - Release Planning Example Questions

Test your knowledge of Release Planning

Question 1

A project's release schedule has been delayed multiple times and stakeholders are getting frustrated. The project manager decides to implement Agile Release Planning. Which of the following would NOT be part of this approach?

Question 2

During a product release planning session, the team realizes they may not be able to complete all the features they initially planned. What should the team do?

Question 3

An Agile project team is planning their releases for the next quarter. The product owner requests several high-priority features to be included in the first release. However, team members express concerns about the available resources. What should the team do?