Sprint Burndown
The Sprint Burndown is a graphical representation of work left to do versus time. The horizontal axis represents time, and the vertical axis represents work remaining, typically it is updated every day. The Sprint Burndown provides a simple view of the Sprint progress and typically includes a line …
PSM I - Sprint Burndown Example Questions
Test your knowledge of Sprint Burndown
Question 1
A sprint is halfway through, and the burndown chart reveals a downward trend indicating that the team is completing tasks much quicker than anticipated. What should the Scrum Master do?
Question 2
The Sprint Burndown chart shows that the team finishes tasks late in the Sprint. The Scrum Team is stressed. As a Scrum Master, how should you respond?
Question 3
The Sprint Burndown chart shows that the team finishes tasks early in the Sprint. What conclusions can be drawn?