Increment

5 minutes 5 Questions

An Increment is the sum of all the Product Backlog items completed during a Sprint and all previous Sprints. It is a body of inspectable, done work that supports empiricism at the end of the Sprint. The Increment must be in a usable condition, regardless of whether or not the Product Owner decides …

Test mode:
PSM I - Increment Example Questions

Test your knowledge of Increment

Question 1

In the middle of an increment, a team member quits the team. How should this scenario be managed?

Question 2

Which of the following scenarios are ideal for utilizing the Agile increment approach to project management?

Question 3

A project team in the middle of an increment receives feedback that the user interface design should be improved. What is the appropriate action to manage this feedback?

More Increment questions
16 questions (total)